At the monthly meeting, the production manager presented the results of a new contract. The production plan had been met, costs were within budget, and the goods had shipped on time.
Sales confirmed that the customer had been invoiced for €600,000. The total cost of the job was €360,000, leaving a difference of €240,000, or 40% of revenue.
When it was her turn, the finance director brought up the materials supplier’s invoice. It was for €240,000 and fell due on Friday.
After covering commitments for its other work, the company had €220,000 available for this job.
The managing director asked when the customer’s payment was expected.
The goods had shipped. When would the cash arrive?
The customer had agreed to pay 60 days after delivery and invoicing. The goods had arrived two weeks earlier. Payment was still about six weeks away.
The materials supplier had granted 30 days from receipt. The materials had arrived two weeks before the finished goods were shipped, so the supplier’s invoice was already coming due.
The customer was meeting its obligations. The supplier was asking to be paid on the agreed date. Production had completed the work as planned.
The finance director then opened the remaining payments for the job. Another €120,000 for labor, energy, subcontracted processing, and transport would fall due before the customer paid.
| Payment or funding | Amount |
|---|---|
| Materials | €240,000 |
| Other payments for the job | €120,000 |
| Total payments due | €360,000 |
| Cash available for that period | €220,000 |
| Additional funding required | €140,000 |
The materials invoice was due in a few days. The remaining payments would follow over the coming weeks. The €600,000 customer payment was expected after those obligations fell due.
What was missing when the deal was agreed?
Sales had checked the price and the customer’s terms. Production had confirmed capacity and delivery dates. Purchasing had secured the materials.
The cost calculation showed the expected margin. The supplier’s payment date and the customer’s payment date were recorded in the documents. But when the job was approved, nobody had put those dates alongside the cash available to fund it.
Had they done so, they would have seen the need for another €140,000 while there was still time to arrange funding and include its cost in the decision.
Now the goods had shipped, and the supplier’s invoice was due in a few days.
What should the next report show?
Finance prepared a payment schedule through to the expected customer receipt. Management could see how much funding was needed, when it would be needed, and how long the company would need to use it.
For subsequent large orders, the same check became part of approving the terms offered to the customer.
Alongside sales value, cost, and delivery date, the review now included the lowest projected cash balance, the week it would occur, and the additional funding required.
That gave management time to consider delivery schedules, payment terms, and funding before making the commitment.